Back to Learning Center

Collin County · TX

Solar permitting in McKinney, TX

Verified submittal requirements and process notes for residential rooftop solar in McKinney. This page is generated from the same database TexPTO uses to drive its in-app checklists — when we update a requirement here, the live product reflects it within minutes.

Utility

Oncor

Interconnection portal

Submission method

Online portal

Average review

10 days

Total to PTO ~20 days

SolarAPP+

Not accepted

Submittal requirements

11 items

  1. #1

    Project Permit Transmittal Letter

    Contractor cover letter that introduces the submittal package to the plan reviewer. Editable before sending.

    McKinney note: This is the installer's cover letter — not a PE-stamped engineering document. Any engineering opinion is provided separately by your licensed PE.

    Auto-generated
  2. #2

    Stamped Engineer Letter (PE-sealed)

    Licensed Professional Engineer's letter attesting to structural adequacy of the roof for the proposed PV array.

    McKinney note: McKinney requires a TX-licensed PE seal on structural letters. Upload the PE-sealed PDF here. TexPTO does not generate engineering opinions.

    Upload required
  3. #3

    Stamped Engineer Structural Drawings

    PE-stamped structural drawings showing roof framing, attachment locations, and load path.

    McKinney note: Provided by your licensed PE.

    Upload required
  4. #4

    Stamped Engineer Electrical Drawings

    PE-stamped electrical drawings including single-line diagram, wiring layout, and disconnect locations.

    McKinney note: Provided by your licensed PE.

    Upload required
  5. #5

    Solar Panel Specifications (Cut Sheets)

    Manufacturer datasheets for panels, inverters, and (if applicable) batteries.

    McKinney note: Upload each manufacturer datasheet. The submittal package concatenates them in order.

    Compiled from sources
  6. #6

    NEC Warning Labels

    NEC-mandated placards (rapid shutdown, PV disconnect, dual power source, etc.) sized for label printing. Requires DC voltage/current values from your design.

    McKinney note: The generator will fail safely if the DC max voltage and max current aren't known — you'll be prompted to provide them. Use the 'Edit specs' button on this row to override extracted values.

    Auto-generated
  7. #7

    Portal Submission Cheat Sheet

    One-page reference with values to paste into McKinney's permit portal. Print or keep on a second monitor while submitting.

    McKinney note: Not a substitute for submission — installer still types values into the portal manually. TexPTO does not automate portal submissions.

    Auto-generated
  8. #8

    HOA Approval Request Letter (draft)

    AI-drafted letter to the homeowner's HOA requesting approval for the solar installation. Review, edit, and sign before sending.

    McKinney note: Varies by subdivision in McKinney. Check deed restrictions.

    Template-drafted
  9. #9

    Project Narrative (draft)

    AI-drafted one-page narrative summarizing the project for the permit reviewer. Attach to submittal or paste into portal text areas.

    McKinney note: If the project is in McKinney's Historic Preservation Overlay (roughly ZIP 75069 core), the narrative should address visibility from the public right-of-way and note whether the HPC has reviewed. Non-historic areas can ignore this.

    Template-drafted
  10. #10

    Portal 'Description of Work' Blurb (draft)

    Short AI-drafted blurb sized to paste into the AHJ portal's Description of Work field (typically 150-250 words).

    McKinney note: Tailor the blurb to McKinney's portal field length if needed — some portals cap at 250 chars, others allow a paragraph.

    Template-drafted
  11. #11

    Historic Preservation Commission Review (if applicable)

    For properties in McKinney's Historic Preservation Overlay, a Certificate of Appropriateness from the HPC must precede the building permit.

    McKinney note: Only applies to properties in the HPC overlay (roughly downtown / West McKinney). If your project isn't in the overlay, skip this requirement.

    Upload required

Common rejection reasons

The most frequent reasons Oncor or McKinney kicks back a residential solar permit. Avoid these on your first submittal to skip a 7–14 day correction cycle.

  • Module/inverter mismatch between plans and spec sheets
  • Missing required safety placard content
  • Incomplete roof/array layout fire-access dimensions
  • Missing Rapid Shutdown placard (NEC 690.12)
  • VLLD distance exceeded (>10 ft Oncor limit)
  • Missing meter or disconnect photo documentation

Workflow stages

  1. 1

    Address Match

    Resolve jurisdiction + utility from service address.

  2. 2

    Package Build

    Generate AHJ-ready permit package JSON and PDF.

  3. 3

    Internal QA

    Validate diagrams, placards, and utility requirements.

  4. 4

    AHJ Submission

    Submit package through AHJ portal workflow.

  5. 5

    Utility Interconnection

    Submit utility packet and track approval milestones.

Run a McKinney project through TexPTO

TexPTO automates the submittal package for McKinney: NEC labels, transmittal letter, portal cheat-sheet, HOA approval letter, and the full requirement checklist above. Enter an address, generate the package, ship it.

Information accurate to TexPTO's curated database as of the most recent review. Contractors should always verify against the AHJ's current published requirements before submitting a permit.